JGM was asked to offload a 35,000 lb. sand heater at a remote mining site in northeastern Arizona. Our field crew mobilized on a Saturday afternoon and were standing by with a 150-ton crane and several light towers in order to make the pick. The truck finally pulled in around 8 p.m. and the unit was safely offloaded that night onto dunnage, ready for installation the following day.
Client
Preferred Sands
Location
Sanders, AZ
Timeline
1 Day