W.L. Gore was expanding their facility in Elkton, Md. and called on JGM to provide a turnkey package for their new world-class manufacturing facility. This project involved the fabrication and erection of girder trusses in excess of 100 feet.

These girder trusses not only served as a clear span roof, but also were supporting a diamond plate mezzanine structure for the plant. This enabled the space below to be column-free. JGM used a 110-ton hydraulic crane to set the trusses. There were a total of ten trusses that were delivered by three trailers.

These trailers required over-length permitting. We had to accept delivery by 7 a.m. and set the trusses by 10 a.m. to avoid any interruptions to employee parking.

Client

Commonwealth Construction

Location

Elkton, MD

Timeline

6 Months

enewsletter signup

Receive monthly updates from JGM and stay in the know.

© Copyright 2024 Privacy Policy Sitemap