JGM springs into action to complete a project before a major Nor’easter snowstorm was set to hit the area.  JGM was the first to be called by a long-time mining client, who had an unfortunate roof collapse and needed emergency service.  JGM mobilized our Engineering & Construction teams on-site to put together a comprehensive plan to safely demo the existing roof and install a new permanent roof bracing the walls.  All engineering and shop drawings were completed in 48 hours.  Our fabrication shop fabricated all new steel over 2 shifts.  We added temporary scaffolding to protect critical equipment below to not have it damaged any further.

Client

Long-time mining client

Location

confidential

enewsletter signup

Receive monthly updates from JGM and stay in the know.