JGM was contacted by Maxim Crane Works to establish a rigging plan for the setting of five new sections of a transmission tower along the Sparta Transmission Tower Line.

Each section of the new tower weighed in excess of 80,000 pounds and was connected by utilizing over 100 bolts at each flange section.

A safe and accurate lift was critical to the success of this project. JGM’s team worked with Maxim to develop a detailed plan of execution and supplied all NCCCO Certified riggers to ensure an efficient, secure and precise installation.

Client

Maxim Crane Works

Location

Sparta, NJ

Timeline

4 Days

enewsletter signup

Receive monthly updates from JGM and stay in the know.

© Copyright 2024 Privacy Policy Sitemap